CLuCH Portfolio

Executive Summary

20 Projects
15 Active
$2.8B Portfolio Value
Q4 2025 Period
Cost & Schedule
1.05
CPI
0.98
SPI
+$42M
Variance
Health, Safety & Environment
0.15
TRIR
0
Fatalities
0.08
LTIR
Strategic Milestones
94%
Complete
18/22
Critical
5
At Risk

Top Risks & Watch Items

Cold Lake Turnaround Delay
Heavy Oil Equipment delivery 3 weeks behind
Permian Labor Shortage
Unconventional Skilled craft availability at 78%
Baytown Permit Timeline
Low Carbon EPA review extended to Q1

Key Decisions Needed

Dec 15
Baytown Phase 2 FID
$450M funding approval
Dec 20
Permian Gate 3 Review
Proceed to detailed engineering
Jan 8
Cold Lake Scope Change
Turnaround reschedule approval

Q4 Highlights

Rotterdam CCUS achieved mechanical completion LCS
Permian Pad Development 47 wells online Unconv
Beaumont Refinery upgrade FID reached Conv

Year-End Forecast vs Plan

Portfolio Cost
Plan: $2.85B $2.78B
Schedule Performance
Target: 100% 96%
Milestones Delivered
Plan: 24 22
Convention
Low Carbon
Unconventional
Heavy Oil

Convention

8
Projects
6
Active
On Track
Status

Low Carbon Solutions

5
Projects
4
Active
On Track
Status

Unconventional

4
Projects
3
Active
On Track
Status

Heavy Oil

3
Projects
2
Active
Monitor
Status