S-Curve Analysis
Earned Value
PV (Planned)$3509M
EV (Earned)$3459M
AC (Actual)$3521M
CV (Cost Var)$-61M
SV (Sched Var)$-50M
EAC (Estimate)$2.4B
Phase Progress
ENG
100.0%
PROC
92.0%
CIV
100.0%
STR
88.0%
MECH
62.0%
Key Milestones
FID (Final Investment Decision)
2023-01-15
FEED Complete
2023-06-30
Detailed Engineering 90%
2024-03-31
First Concrete Pour
2024-04-01
Quality
31
Punch Open
6
NCRs Open
93.1%
Weld Pass
78.3%
Insp Pass
Schedule
Critical Activities
Float Days (Avg)
days
Weather Delays
days
Target Completion
Q2 2026
Resources
Peak Workforce
1211
Current Workforce
70
Equipment Active
10
Equip Utilization
73%